Road Projects

______________________________________________________________________________

The Village of Little Chute Department of Public Works is constantly undertaking a variety of projects ranging form road construction, water and sewer replacement and storm water management. Throughout the course of the year, road project updates will be available.

Intersection of Evergreen and Holland Road Construction -
Monday August 26th

Contractor will be temporarily shutting down the northbound (eastern half) lane on the north side of the intersection of Evergreen and Holland on Monday, August 26th, to complete the sanitary sewer pipe extension.  This closure is just a temporary condition during working hours and a few hundred feet at most will be affected.  The contractor anticipates that the work will only take a day or two to complete.


Updated Weekly Schedule, Friday August 23

2019 UTILITY & STREET CONSTUCTION – EVERGREEN DRIVE

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of reconstructing approximately 5,230 centerline feet of roadway along Evergreen Drive from French Road to Holland Road in the Village of Little Chute, Outagamie County, Wisconsin.  The reconstruction project includes the following: replacement of the existing roadway, removal of any trees within the right-of-way that will be in conflict with utility or paving operation, storm sewer utility installation, sanitary sewer manhole adjustments, water main lowering, future utility stub outs for storm sewer, water main and sanitary sewer, reconstructing all side road intersections to match point, installing concrete curb & gutter, installation of reinforced (doweled) concrete pavement, and associated driveway and lawn restoration work.  The proposed roadway will be converted from a rural to urban typical section and widened from its current width (approximately 23-feet) to be 38-feet from face of curb to face of curb.  The proposed widening will include two (2) 12-foot drive lanes and a 14-foot two-way left turn lane.  The proposed roadway will be contained within the current 66-foot right-of-way.


Updated Weekly Schedule (August 26th to August 30th)

EVERGREEN DRIVE UTILITIES

Work is scheduled to continue with the installation of storm sewer and relocation of private utilities. Don Hietpas & Sons is working on Evergreen Drive and will continue work on storm sewer main from their current location between Cherryvale & Holland, work will continue east and will extend into the intersection of Evergreen and Holland Rd.  Hietpas second crew will be assisting with water and storm sewer utility construction in various locations between N. French Rd. and Holland Rd until project completion. Hietpas anticipates project completion for utility work during the middle part of the week of August 28th

EVERGREEN DRIVE PAVING

Vinton Construction is the general contractor for the Village paving contract on Evergreen Drive. Vinton has completed the road grading portion between Cherryvale Avenue and French Road this week. Vinton will continue grading work in preparation for concrete pavement east of Cherryvale, work will continue east toward Holland Road. Evergreen Drive is an active construction site. For your safety as well as those working in the area, please avoid use when possible.  

Traffic Impacts: Evergreen Drive is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities.



2019 ASPHALT PAVING PROJECTS - PARK AVENUE ASPHALT PAVING

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of asphalt paving approximately 7,200 square yards. The utilities under the pavement are in good condition and will not require replacement.  This project will include the removal of the existing asphalt and gravel base.  The subgrade will be reshaped and compacted.  Finally, a new gravel base and asphalt pavement will be installed.  Additional work will include rim adjustment of structures and replacement of damaged curb and gutter in spot locations.

Updated Weekly Schedule (August 26th to August 30th)

CREEKVIEW PARK TRAIL

Creekview Park is located at 900 Harvest Trail in the Village of Little Chute. MCC, Inc. is the General Contractor for the Village asphalt paving contract.  MCC has completed the placement of the asphalt pavement. Crews are scheduled to work on grading & restoration at the end of this week.

PARK AVENUE - PRIVATE UTILITIES

Michels Corporation has completed the installation of new gas main and services for We-Energies on Park Avenue. Michels sub-contractor has completed the replacement of disturbed sidewalk, curb & gutter and landscape restoration where necessary.

PARK AVENUE PAVING

MCC’s sub-contractor has completed the manhole spot repairs and water valve box adjustments. MCC also completed the milling and removal of existing asphalt pavement on Park Avenue. MCC’s concrete sub-contractor Martell, has completed the curb and gutter removal and replacement. MCC’s crews completed manhole adjustments and fine grading last week. Asphalt pavement is scheduled for the early part of the week of August 26th.

Traffic Impacts: Park Avenue is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Driveway access will be maintained with limited restrictions as necessary for project constructability.  Park Avenue is an active construction site. For your safety as well as those working in the area, please avoid use when possible.




Updated Weekly Schedule, Friday August 16th


2019 UTILITY & STREET CONSTRUCTION – EVERGREEN DRIVE

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of reconstructing approximately 5,230 centerline feet of roadway along Evergreen Drive from French Road to Holland Road in the Village of Little Chute, Outagamie County, Wisconsin.  The reconstruction project includes the following: replacement of the existing roadway, removal of any trees within the right-of-way that will be in conflict with utility or paving operation, storm sewer utility installation, sanitary sewer manhole adjustments, water main lowering, future utility stub outs for storm sewer, water main and sanitary sewer, reconstructing all side road intersections to match point, installing concrete curb & gutter, installation of reinforced (doweled) concrete pavement, and associated driveway and lawn restoration work.  The proposed roadway will be converted from a rural to urban typical section and widened from its current width (approximately 23-feet) to be 38-feet from face of curb to face of curb.  The proposed widening will include two (2) 12-foot drive lanes and a 14-foot two-way left turn lane.  The proposed roadway will be contained within the current 66-foot right-of-way.

Updated Weekly Schedule (August 19th to August 23rd)

EVERGREEN DRIVE UTILITIES

Work is scheduled to continue with the installation of storm sewer and relocation of private utilities. Don Hietpas & Sons is working on Evergreen Drive and will continue work on storm sewer main from their current location between Cherryvale & Holland, work will continue east toward Holland Rd.  Hietpas second crew will be assisting with water and storm sewer utility construction in various locations between N. French Rd. and Holland Rd until project completion. Hietpas anticipates project completion during the following week of August 26th

EVERGREEN DRIVE PAVING

Vinton Construction is the general contractor for the Village paving contract on Evergreen Drive.  Vinton has begun excavation and grading work on Evergreen Drive.  Vinton is scheduled to continue grading operations between Cherryvale Avenue and French Road this week.  Evergreen Drive is an active construction site. For your safety as well as those working in the area, please avoid use when possible.  

Traffic Impacts: Evergreen Drive is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities.

2019 ASPHALT PAVING PROJECTS - PARK AVENUE ASPHALT PAVING

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of asphalt paving approximately 7,200 square yards. The utilities under the pavement are in good condition and will not require replacement.  This project will include the removal of the existing asphalt and gravel base.  The subgrade will be reshaped and compacted.  Finally, a new gravel base and asphalt pavement will be installed.  Additional work will include rim adjustment of structures and replacement of damaged curb and gutter in spot locations.

Updated Weekly Schedule (August 19th to August 23rd)

CREEKVIEW PARK TRAIL

Creekview Park is located at 900 Harvest Trail in the Village of Little Chute. MCC, Inc. is the General Contractor for the Village asphalt paving contract.  MCC has completed the placement of the asphalt pavement. Crews are scheduled to work on grading & restoration at the end of this week.

PARK AVENUE - PRIVATE UTILITIES

Michels Corporation has completed the installation of new gas main and services for We-Energies on Park Avenue. Michels sub-contractor is scheduled to be on-site this week continuing the replacement of disturbed sidewalk, curb & gutter and landscape restoration where necessary. Access to driveways may be limited during concrete placement and restoration if curb and gutter replacement is needed in specific locations.   

PARK AVENUE PAVING

MCC’s sub-contractor has completed the manhole spot repairs and water valve box adjustments. MCC also completed the milling and removal of existing asphalt pavement on Park Avenue. MCC’s concrete sub-contractor Martell, has completed the curb and gutter removal and replacement. MCC’s crews are scheduled to work on manhole adjustments and fine grading this week. Asphalt pavement is scheduled for the following week of August 26th.

Traffic Impacts: Park Avenue is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Driveway access will be maintained with limited restrictions as necessary for project constructability.  Park Avenue is an active construction site. For your safety as well as those working in the area, please avoid use when possible.




Updated Weekly Schedule, Friday August 9th



2019 UTILITY & STREET CONSTUCTION – EVERGREEN DRIVE

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of reconstructing approximately 5,230 centerline feet of roadway along Evergreen Drive from French Road to Holland Road in the Village of Little Chute, Outagamie County, Wisconsin.  The reconstruction project includes the following: replacement of the existing roadway, removal of any trees within the right-of-way that will be in conflict with utility or paving operation, storm sewer utility installation, sanitary sewer manhole adjustments, water main lowering, future utility stub outs for storm sewer, water main and sanitary sewer, reconstructing all side road intersections to match point, installing concrete curb & gutter, installation of reinforced (doweled) concrete pavement, and associated driveway and lawn restoration work.  The proposed roadway will be converted from a rural to urban typical section and widened from its current width (approximately 23-feet) to be 38-feet from face of curb to face of curb.  The proposed widening will include two (2) 12-foot drive lanes and a 14-foot two-way left turn lane.  The proposed roadway will be contained within the current 66-foot right-of-way.

Updated Weekly Schedule (August 12th to August 16th)

Work is scheduled to continue with the installation of storm sewer and relocation of private utilities. Don Hietpas & Sons is working on Evergreen Drive and will continue work on storm sewer main from their current location between Cherryvale & Holland, work will continue east toward Holland Rd.  Hietpas second crew will be assisting with water and storm sewer utility construction in various locations between N. French Rd. and Holland Rd until project completion. Evergreen Drive is an active construction site. For your safety as well as those working in the area, please avoid use when possible.

Traffic Impacts: Evergreen Drive is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities.

2019 ASPHALT PAVING PROJECTS - PARK AVENUE ASPHALT PAVING

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of asphalt paving approximately 7,200 square yards. The utilities under the pavement are in good condition and will not require replacement.  This project will include the removal of the existing asphalt and gravel base.  The subgrade will be reshaped and compacted.  Finally, a new gravel base and asphalt pavement will be installed.  Additional work will include rim adjustment of structures and replacement of damaged curb and gutter in spot locations.

Updated Weekly Schedule, (August 12th to August 16th)

CREEKVIEW PARK TRAIL

Creekview Park is located at 900 Harvest Trail in the Village of Little Chute. MCC, Inc. is the General Contractor for the Village asphalt paving contract.  MCC has completed the placement of the asphalt pavement. Crews are scheduled to work on grading & restoration this week.

PARK AVENUE - PRIVATE UTILITIES

Michels Corporation has completed the installation of new gas main and services for We-Energies on Park Avenue. Michels sub-contractor is scheduled to be on-site this week performing replacement of disturbed sidewalk, curb & gutter and landscape restoration where necessary.  

PARK AVENUE PAVING

MCC’s sub-contractor has completed the manhole spot repairs and water valve box adjustments. MCC also completed the milling and removal of existing asphalt pavement on Park Avenue. MCC’s concrete sub-contractor Martell, has completed the curb and gutter removal. Martell’s crews are scheduled to form and place new concrete curb and gutter this week. Access to driveways may be limited during concrete placement and restoration if curb and gutter replacement is needed in specific locations. 

   Traffic Impacts: Park Avenue is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Driveway access will be maintained with limited restrictions as necessary for project constructability. Park Avenue is an active construction site. For your safety as well as those working in the area, please avoid use when possible.






Project Update, Friday, August 2nd

2019 UTILITY & STREET CONSTUCTION – EVERGREEN DRIVE

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of reconstructing approximately 5,230 centerline feet of roadway along Evergreen Drive from French Road to Holland Road in the Village of Little Chute, Outagamie County, Wisconsin.  The reconstruction project includes the following: replacement of the existing roadway, removal of any trees within the right-of-way that will be in conflict with utility or paving operation, storm sewer utility installation, sanitary sewer manhole adjustments, water main lowering, future utility stub outs for storm sewer, water main and sanitary sewer, reconstructing all side road intersections to match point, installing concrete curb & gutter, installation of reinforced (doweled) concrete pavement, and associated driveway and lawn restoration work.  The proposed roadway will be converted from a rural to urban typical section and widened from its current width (approximately 23-feet) to be 38-feet from face of curb to face of curb.  The proposed widening will include two (2) 12-foot drive lanes and a 14-foot two-way left turn lane.  The proposed roadway will be contained within the current 66-foot right-of-way.

Updated Weekly Schedule (August 5th to August 9th)

Work is scheduled to continue with the installation of storm sewer and relocation of private utilities. Don Hietpas & Sons is working on Evergreen Drive and will continue work on the 36” storm sewer main from their current location of approximately 1400 feet east of Cherryvale, work will continue east toward Holland Rd.  Hietpas will be bringing in a second crew to assist with utility construction. Evergreen Drive is an active construction site. For your safety as well as those working in the area, please avoid use when possible.

Traffic Impacts: Evergreen Drive is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities.

2019 ASPHALT PAVING PROJECTS - PARK AVENUE ASPHALT PAVING

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of asphalt paving approximately 7,200 square yards. The utilities under the pavement are in good condition and will not require replacement.  This project will include the removal of the existing asphalt and gravel base.  The subgrade will be reshaped and compacted.  Finally, a new gravel base and asphalt pavement will be installed.  Additional work will include rim adjustment of structures and replacement of damaged curb and gutter in spot locations.

Updated Weekly Schedule (August 5th to August 9th)

CREEKVIEW PARK TRAIL

Creekview Park is located at 900 Harvest Trail in the Village of Little Chute. MCC, Inc. is the General Contractor for the Village asphalt paving contract.  MCC has completed the placement of the asphalt pavement. Crews are scheduled to work on grading & restoration this week.

PARK AVENUE - PRIVATE UTILITIES

Michels Corporation has been contracted to replace the gas main and services for We-Energies on Park Avenue.  Michels is scheduled to continue work on Park Avenue in various locations throughout the week.

PARK AVENUE PAVING

MCC’s sub-contractor has completed the manhole spot repairs and water valve box adjustments. MCC also completed the milling and removal of existing asphalt pavement on Park Avenue. MCC is scheduled to begin the excavation and grading of base course material on Park Avenue for the entire week and into next week. Access to driveways will be maintained at the end of each work day during grading. 

   Traffic Impacts: Park Avenue is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Driveway access will be maintained with limited restrictions as necessary for project constructability. Park Avenue is an active construction site. For your safety as well as those working in the area, please avoid use when possible.



Project Update, Monday, July 29th




2019 UTILITY & STREET CONSTUCTION – EVERGREEN DRIVE


Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of reconstructing approximately 5,230 centerline feet of roadway along Evergreen Drive from French Road to Holland Road in the Village of Little Chute, Outagamie County, Wisconsin.  The reconstruction project includes the following: replacement of the existing roadway, removal of any trees within the right-of-way that will be in conflict with utility or paving operation, storm sewer utility installation, sanitary sewer manhole adjustments, water main lowering, future utility stub outs for storm sewer, water main and sanitary sewer, reconstructing all side road intersections to match point, installing concrete curb & gutter, installation of reinforced (doweled) concrete pavement, and associated driveway and lawn restoration work.  The proposed roadway will be converted from a rural to urban typical section and widened from its current width (approximately 23-feet) to be 38-feet from face of curb to face of curb.  The proposed widening will include two (2) 12-foot drive lanes and a 14-foot two-way left turn lane.  The proposed roadway will be contained within the current 66-foot right-of-way.

Updated Weekly Schedule (July 29th to August 2nd)

Work is scheduled to continue with the installation of storm sewer and relocation of private utilities. Don Hietpas & Sons is working on Evergreen Drive and will work on the 54” storm sewer main from approximately 800 feet east of Cherryvale, work will continue east toward Holland Rd.  Evergreen Drive is an active construction site. For your safety as well as those working in the area, please avoid use when possible.

Traffic Impacts: Evergreen Drive is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities.

2019 ASPHALT PAVING PROJECTS - PARK AVENUE ASPHALT PAVING

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of asphalt paving approximately 7,200 square yards. The utilities under the pavement are in good condition and will not require replacement.  This project will include the removal of the existing asphalt and gravel base.  The subgrade will be reshaped and compacted.  Finally, a new gravel base and asphalt pavement will be installed.  Additional work will include rim adjustment of structures and replacement of damaged curb and gutter in spot locations.

Updated Weekly Schedule (July 29th to August 2nd)

CREEKVIEW PARK TRAIL

Creekview Park is located at 900 Harvest Trail in the Village of Little Chute. MCC, Inc. is the General Contractor for the Village asphalt paving contract.  Excavation for the asphalt trail in Creekview Park, as well as the placement of the stone base material have been completed. Fine grading for the asphalt trail will take place during the early part of the week. Asphalt placement is scheduled between the middle to the end of the week.

PARK AVENUE - PRIVATE UTILITIES

Michels Corporation has been contracted to replace the gas main and services for We-Energies on Park Avenue.  Michels is scheduled to continue work on Park Avenue in various locations throughout the week.

PARK AVENUE PAVING

MCC’s milling and asphalt removal operation were postponed due to weather. MCC anticipates starting the existing asphalt pavement removals for Park Avenue on August 2nd. Initial location of milling operations to be determined by MCC in coordination with the construction of the new gas main mentioned above. MCC’s utility sub-contractor will continue manhole spot repairs and adjustments for the water valve boxes. 

   Traffic Impacts: Park Avenue is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Driveway access will be maintained with limited restrictions as necessary for project constructability. Park Avenue is an active construction site. For your safety as well as those working in the area, please avoid use when possible.



Project Update, Friday, July 19th

2019 UTILITY & STREET CONSTUCTION – EVERGREEN DRIVE

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of reconstructing approximately 5,230 centerline feet of roadway along Evergreen Drive from French Road to Holland Road in the Village of Little Chute, Outagamie County, Wisconsin.  The reconstruction project includes the following: replacement of the existing roadway, removal of any trees within the right-of-way that will be in conflict with utility or paving operation, storm sewer utility installation, sanitary sewer manhole adjustments, water main lowering, future utility stub outs for storm sewer, water main and sanitary sewer, reconstructing all side road intersections to match point, installing concrete curb & gutter, installation of reinforced (doweled) concrete pavement, and associated driveway and lawn restoration work.  The proposed roadway will be converted from a rural to urban typical section and widened from its current width (approximately 23-feet) to be 38-feet from face of curb to face of curb.  The proposed widening will include two (2) 12-foot drive lanes and a 14-foot two-way left turn lane.  The proposed roadway will be contained within the current 66-foot right-of-way.

Updated Weekly Schedule (July 22nd to July 26th)

Work is scheduled to continue with the installation of storm sewer and relocation of private utilities. Don Hietpas & Sons continues work on Evergreen Drive and will work on final adjustments for manholes and inlets located between Cherryvale Avenue & French Road for the first part of the week.  Hietpas will then begin installation of 54” storm main near Cherryvale and will work east toward Holland Rd.  Evergreen Drive is an active construction site. For your safety as well as those working in the area, please avoid use when possible.

Traffic Impacts: Evergreen Drive is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities.

2019 ASPHALT PAVING PROJECTS - PARK AVENUE ASPHALT PAVING

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of asphalt paving approximately 7,200 square yards. The utilities under the pavement are in good condition and will not require replacement.  This project will include the removal of the existing asphalt and gravel base.  The subgrade will be reshaped and compacted.  Finally, a new gravel base and asphalt pavement will be installed.  Additional work will include rim adjustment of structures and replacement of damaged curb and gutter in spot locations.

Updated Weekly Schedule (July 22nd to July 26th)

CREEKVIEW PARK TRAIL

MCC, Inc. is the General Contractor for the Village asphalt paving contract.  Excavation for the asphalt trail in Creekview Park, located at 900 Harvest Trail has begun. Work will continue with the excavation of the trail area and the placement of the stone base material in preparation for the asphalt surface.

PARK AVENUE - PRIVATE UTILITIES

Michels Corporation has been contracted to replace the gas main and services for We-Energies on Park Avenue.  Michels is scheduled to continue work on Park Avenue in various locations throughout the week.

PARK AVENUE PAVING

MCC’s milling and asphalt removal operation were postponed due to weather. MCC anticipates starting the existing asphalt pavement removals for Park Avenue on August 2nd. Initial location of milling operations to be determined by MCC in coordination with the construction of the new gas main mentioned above. 

   Traffic Impacts: Park Avenue is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Driveway access will be maintained with limited restrictions as necessary for project constructability. Park Avenue is an active construction site. For your safety as well as those working in the area, please avoid use when possible.





Project Update, Friday, July 12th

2019 UTILITY & STREET CONSTUCTION – EVERGREEN DRIVE

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of reconstructing approximately 5,230 centerline feet of roadway along Evergreen Drive from French Road to Holland Road in the Village of Little Chute, Outagamie County, Wisconsin.  The reconstruction project includes the following: replacement of the existing roadway, removal of any trees within the right-of-way that will be in conflict with utility or paving operation, storm sewer utility installation, sanitary sewer manhole adjustments, water main lowering, future utility stub outs for storm sewer, water main and sanitary sewer, reconstructing all side road intersections to match point, installing concrete curb & gutter, installation of reinforced (doweled) concrete pavement, and associated driveway and lawn restoration work.  The proposed roadway will be converted from a rural to urban typical section and widened from its current width (approximately 23-feet) to be 38-feet from face of curb to face of curb.  The proposed widening will include two (2) 12-foot drive lanes and a 14-foot two-way left turn lane.  The proposed roadway will be contained within the current 66-foot right-of-way.

Updated Weekly Schedule (July 15th to July 19th)

Work is scheduled to continue with the installation of storm sewer and relocation of private utilities. Don Hietpas & Sons continues work on Evergreen Drive and will work on the installation of storm inlets and yard drains between Cherryvale Avenue & French Road for the first part of the week.  Hietpas will then begin installation of 54” storm main near Cherryvale and will work east toward Holland Rd.  Evergreen Drive is an active construction site. For your safety as well as those working in the area, please avoid use when possible.

Traffic Impacts: Evergreen Drive is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities.

2019 ASPHALT PAVING PROJECTS - PARK AVENUE ASPHALT PAVING

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of asphalt paving approximately 7,200 square yards. The utilities under the pavement are in good condition and will not require replacement.  This project will include the removal of the existing asphalt and gravel base.  The subgrade will be reshaped and compacted.  Finally, a new gravel base and asphalt pavement will be installed.  Additional work will include rim adjustment of structures and replacement of damaged curb and gutter in spot locations.

Updated Weekly Schedule (July 15th to July 19th)

Michels Corporation has been contracted to replace the gas main and services for We-Energies on Park Avenue.  Michels is scheduled to continue work on Park Avenue in various locations throughout the week.

MCC, Inc. is the General Contractor for the Village asphalt paving contract.  Excavation for the asphalt trail in Creekview Park, located at 900 Harvest Trail is scheduled for the early part of this week. MCC also has plans to begin milling and removals of the existing asphalt pavement on Park Avenue on July 18th. Initial location of milling operations to be determined by MCC in coordination with the construction of the new gas main mentioned above. 

Traffic Impacts: Park Avenue is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Driveway access will be maintained with limited restrictions as necessary for project constructability. Park Avenue is an active construction site. For your safety as well as those working in the area, please avoid use when possible.


201Project Update, Friday, June 28th

9 UTILITY & STREET CONSTUCTION – EVERGREEN DRIVE

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of reconstructing approximately 5,230 centerline feet of roadway along Evergreen Drive from French Road to Holland Road in the Village of Little Chute, Outagamie County, Wisconsin.  The reconstruction project includes the following: replacement of the existing roadway, removal of any trees within the right-of-way that will be in conflict with utility or paving operation, storm sewer utility installation, sanitary sewer manhole adjustments, water main lowering, future utility stub outs for storm sewer, water main and sanitary sewer, reconstructing all side road intersections to match point, installing concrete curb & gutter, installation of reinforced (doweled) concrete pavement, and associated driveway and lawn restoration work.  The proposed roadway will be converted from a rural to urban typical section and widened from its current width (approximately 23-feet) to be 38-feet from face of curb to face of curb.  The proposed widening will include two (2) 12-foot drive lanes and a 14-foot two-way left turn lane.  The proposed roadway will be contained within the current 66-foot right-of-way.

Updated Weekly Schedule (June 24th to June 28th)

Work is scheduled to continue with the installation of storm sewer and relocation of private utilities. Don Hietpas & Sons is working on the installation of 48” storm sewer between Cherryvale Ave. & French Road on Evergreen Drive, work is scheduled to continue west toward French Road. Evergreen Drive is an active construction site. For your safety as well as those working in the area, please avoid use when possible.

Traffic Impacts: Evergreen Drive is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities.

2019 ASPHALT PAVING PROJECTS - PARK AVENUE ASPHALT PAVING

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of asphalt paving approximately 7,200 square yards. The utilities under the pavement are in good condition and will not require replacement.  This project will include the removal of the existing asphalt and gravel base.  The subgrade will be reshaped and compacted.  Finally, a new gravel base and asphalt pavement will be installed.  Additional work will include rim adjustment of structures and replacement of damaged curb and gutter in spot locations.

Project Schedule

Michels Corporation has been contracted to replace the gas main and services for We-Energies on Park Avenue.  Michels is scheduled to begin work on Park Avenue near Buchanan Street beginning the week of July 1st.

MCC, Inc. is the General Contractor for the Village paving contract and is scheduled to begin Monday July 15th near Wilson Street. 

   Traffic Impacts: Park Avenue is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Driveway access will be maintained with limited restrictions as necessary for project constructability. Park Avenue is an active construction site. For your safety as well as those working in the area, please avoid use when possible.



 Project Update, Friday, June 21st


2019 UTILITY & STREET CONSTUCTION – EVERGREEN DRIVE

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of reconstructing approximately 5,230 centerline feet of roadway along Evergreen Drive from French Road to Holland Road in the Village of Little Chute, Outagamie County, Wisconsin.  The reconstruction project includes the following: replacement of the existing roadway, removal of any trees within the right-of-way that will be in conflict with utility or paving operation, storm sewer utility installation, sanitary sewer manhole adjustments, water main lowering, future utility stub outs for storm sewer, water main and sanitary sewer, reconstructing all side road intersections to match point, installing concrete curb & gutter, installation of reinforced (doweled) concrete pavement, and associated driveway and lawn restoration work.  The proposed roadway will be converted from a rural to urban typical section and widened from its current width (approximately 23-feet) to be 38-feet from face of curb to face of curb.  The proposed widening will include two (2) 12-foot drive lanes and a 14-foot two-way left turn lane.  The proposed roadway will be contained within the current 66-foot right-of-way.

Updated Weekly Schedule (June 24th to June 28th)

Work is scheduled to continue with the installation of storm sewer and relocation of private utilities. Don Hietpas & Sons is working on the installation of 48” storm sewer near the intersection of Cherryvale Ave. & Evergreen Drive, work is scheduled to continue west toward French Road. Evergreen Drive is an active construction site. For your safety as well as those working in the area, please avoid use when possible.

Traffic Impacts: Evergreen Drive is closed to through traffic. It is illegal to drive past a “ROAD CLOSED” sign or to move any construction barricades. Residents, business owners, and customers may access properties past “ROAD CLOSED – LOCAL TRAFFIC ONLY” signs. Parking is not permitted on the street, access for drop off and pick up are allowed. Residents should expect additional restrictions due to installation of proposed utilities.

2019 ASPHALT PAVING PROJECTS - PARK AVENUE ASPHALT PAVING

Schedule: June 2019 to October 2019

Project Description:

The proposed project consists of asphalt paving approximately 7,200 square yards. The utilities under the pavement are in good condition and will not require replacement.  This project will include the removal of the existing asphalt and gravel base.  The subgrade will be reshaped and compacted.  Finally, a new gravel base and asphalt pavement will be installed.  Additional work will include rim adjustment of structures and replacement of damaged curb and gutter in spot locations.

Project Schedule

Work is scheduled to begin on Park Avenue beginning the week of July 8th.

_______________________________________________________________________________

Project Update Monday, June 10th

Project Walk-Thru Dates Have Been Set

West Evergreen Drive – Wednesday, June 12th
For more information click here.

Park Avenue – Wednesday, June 26th
For more information click here.

_______________________________________________________________________________

Bid Documents

To bid on the 2019 utility and street reconstruction projects click the link here and enter the following quest numbers:

Park Avenue Asphalt Paving (2019001)
Quest E-Bid  Doc # 6255729

Evergreen Drive Storm Sewer (2019002)
Quest E-Bid  Doc # 6255906

 Evergreen Drive Concrete Paving (2019003)
Quest E-Bid  Doc # 6255921

West Evergreen Drive

The utility (storm Sewer) and concrete street reconstruction is necessary on West Evergreen Drive to accommodate new development and increased traffic load.  The proposed work includes new concrete pavement with integral curb and gutter, storm sewer, and grass restoration areas. The new pavement on West Evergreen Drive will be comprised of two 12-foot-wide drive lanes and one 14-foot-wide common center turning lane. 

Park Avenue

Asphalt pavement replacement is needed on Park Avenue because it has reached the useful life expectancy of the pavement. Because the utilities are in relatively good condition with curb and gutter requiring only spot repairs it is best to replace the asphalt pavement and not install a 50-year concrete pavement over the ageing infrastructure.  With asphalt being approximately half the cost of concrete at approximately half the life cycle, it is economically more feasible to provide a pavement that will last 20 to 25 years to better match with the utilities life cycle before a total reconstruction is necessary. The existing condition of the asphalt pavement has reached a level where maintenance continues to increase without extending the pavement life.  A pavement overlay is not an option due to the current condition of the pavement and subbase.  To prevent further surface water intrusion and to correct sub-base rutting the pavement will be removed and subbase regraded and compacted prior to placement of granular base material and new asphalt pavement.

Public Informational Meeting – 4/3/19

Click here for meeting outline.

Public Hearing - 4/17/19

Click here for Frequently Asked Questions.

Click here for power point presentation.


WIS 441 Bridge Painting
Project Location:  WIS 441 over Fox River, WIS 96, and Railroad Outagamie County

WISDOT will be conducting a maintenance painting project on the WIS 441 bridge over the Fox River, WIS 96, and Canadian National Railroad. Anticipated work will begin in April 2018.  Work will continue until November 2018 and finish any remaining work in April of 2019.  

WIS 441 will remain open to at least one lane of traffic in each direction at all times during the project.  The single lane closures will be limited to nighttime only from 8:00 pm to 6:00 am.


Thank you for your patience throughout the reconstruction process!